Netherlands reactor restart fixed for the second half of August

The repairs to the High Flux Reactor in Petten, the Netherlands, are proceeding and the date of the restart remains fixed for the second half of August, said the Nuclear Research and Consultancy Group (NRG) of the Netherlands.

The removal of concrete by core drilling was completed on April 23 and the drilling rigs have been removed from the sub-pile room.

The manual removal of the concrete between the drill holes started on April 26. A snapped water tube, part of the cooling system caused flooding in the reactor basement on May 2, resulting in a temporary suspension of the repair and the repair was continued on May 4, the group said.

After the concrete removal, the repair project now proceeds to the welding phase. There have been no safety incidents during the period and the radiation dose levels for internal and external employees have remained well below the planned limits, NRG reported.

Subscribe to Radiology Business News

Innovation at work

DataFirst’s Silverback Workflow Engine combines advanced DICOM routing, an integrated HL7 engine, and intelligent workflow orchestration. Newly added Silverback HarmoniX standardizes inconsistent DICOM study and series descriptions to improve hanging protocol consistency, image presentation, and downstream radiology workflows—all within one unified enterprise imaging platform featured at RSNA 2026.

When he happened upon the CIVIE booth at RBMA PaRADigm 2025, Mina Mousa, MD, had no thoughts of leaving his job at 10-physician Radiology Associates of Tallahassee in Florida.  

Sponsored by CIVIE

A small step for technologists. A meaningful step toward patient-centered contrast dosing. And a benefit that can extend to radiologists. 

Sponsored by Bayer

Subscribe to Radiology Business News

Subscribe to Radiology Business News